Project Profile| Project Title | Construction of New 380/33 KV Ashayrah Wind BSP (WOA), Taif Region, Saudi Arabia — Balance of Plant (BOP), including all civil, structural & precast concrete works, on a design-build basis against Spec No. PTS-25WN366. |
| End Client | National Grid SA (NGSA) — formerly SEC/National Grid, Saudi Arabia |
| Main Contractor (Tier-1) | Elsewedy Electric — PSP Division ("Elsewedy PSP"), referred to as "CONTRACTOR" throughout the tender documents |
| KPC's Role | Precast Concrete Subcontractor ("SUBCONTRACTOR") — reporting to Elsewedy PSP, not directly to National Grid SA |
| Reference Spec | PTS-25WN366 — Final SOW/TS for Construction of New 380/33 KV Ashayrah Wind 380KV BSP (Rev.0, 26-Feb-2026), Appendix-25: Precast Concrete Building |
| BOQ Reference | "Ashayrah Precast Concrete BOQ.xlsx" — Civil BOQ for Construction of New 380/33 KV Ashayrah PV BSP, Rev.00, 14-Apr-2026 |
| Multi-Site Program | The precast building standard is unified across three NGSA BSP sites: Masturah, Al Asharya (this tender), and Al Majmaa — same precast typology, repeatable design intended to reduce mold/variation across sites |
Qualification & Roles
Contract Hierarchy| Contracting Structure | NGSA (Employer) → Elsewedy PSP (Tier-1 Contractor) → KPC Precast (Subcontractor). KPC has no direct contract with NGSA; all approvals, RFIs, and instructions flow through Elsewedy PSP. |
| Governing Standards KPC Must Hold | TES-Q-113.01 (Design Criteria for Precast & Prestressed Concrete Structures), TCS-Q-113.04 (Precast Concrete Works), SEEDS-II (submittal/title block standard). Precast Manufacturer qualification against these standards should be documented in the technical proposal. |
| Guarantee Obligation | KPC/Precast Manufacturer must issue a formal Guarantee Letter certifying the precast system and connections are safe under all loading cases including seismic and diaphragm action — see "Warranty & Guarantee Obligations". |
Not applicableNo joint venture, consortium, or multi-partner structure is referenced anywhere in the tender package for the precast scope — KPC is engaged as a single, standalone subcontractor to Elsewedy PSP.
Commencement
Gated Start| Production Start Gate | Per Appendix-25 Section 4: "CONTRACTOR shall not proceed with production of precast elements unless full interface synchronization with the substructure design has been verified and approved." KPC cannot start fabrication on commencement date alone — it is contingent on substructure design sign-off. |
| Pre-Production Submittals | Structural models/calculations, reaction force summaries, and material pre-approval certificates must be submitted and approved before commencement of production — see Submittal List. |
| Special Techniques Disclosure | Any special fabrication techniques (double casting, insulation methods) must be documented at the outset and included in the baseline schedule — cannot be introduced after commencement without replanning. |
Key Dates
Incomplete Data| Overall Project Duration | 5 months (per Appendix-01 "Schedule.xlsx") |
| Commencement Date | Not populated in the schedule sheet provided — cell is blank |
| Delivery / Completion Date | Not populated in the schedule sheet provided — cell is blank |
| Recommendation | Raise a formal clarification (Appendix-05 Clarification Form) to obtain firm commencement and delivery dates, and the substructure design-freeze date, before finalizing KPC's fabrication and erection program. |
KPC Scope of Work — At a Glance
Precast Only6
Buildings with precast scope
2
Full superstructure buildings (GIS + Control)
4
Roof-slab-only buildings
~4,340 m²
Precast insulated wall panels (GIS + Control, largest items)
45 MPa
Prestressed member concrete grade
| Full Precast Superstructure | 380 KV GIS Building, Control & 33kV SWGR Building — columns, beams, parapets, door canopies, stair flights/landings, double-tee slabs, hollow-core slabs, insulated wall panels, shear walls |
| Roof-Slab-Only Scope | Customer Building, Security Building, Fire Pump Building, Gate Room, Gate Room Toilet, Tunnel Stairs — precast roof/HCS only per the Building List (though the BOQ shows additional wall/column line items for some of these — see "Change in Scope") |
| Ancillary Precast Items | Precast canopies for staircases, precast trench covers (100–200mm), splash blocks (200x200 & 400x400mm), scupper drains, downspout covers, precast curb stones, precast fire-wall panels/columns (Transformer & Reactor bays), precast boundary/fire walls |
| Explicitly Excluded from KPC | Cast-in-place (CIP) substructure/foundations, structural steel works, waterproofing membrane application (KPC supplies embeds only), internal/external paint on precast walls (referred to Architectural BOQ), HVAC/MEP equipment |
Precast BOQ — Key Quantities by Building
From Appendix-04| Building | Precast Element | Qty | Unit |
|---|---|---|---|
| 380 KV GIS Building Full superstructure | Ground columns | 441.6 | m³ |
| Roof beams | 145.8 | m³ | |
| Intermediate beams | 75.9 | m³ | |
| Parapet | 132.5 | m³ | |
| Door canopies | 6.6 | m³ | |
| Stair steps & landings | 37.5 | m³ | |
| Double-T slab, 600mm | 2,320.0 | m² | |
| Hollow core slab, 200mm | 97.6 | m² | |
| Insulated wall panels, 260mm / Shear wall | 4,039.9 / 404.3 | m² | |
| Control & 33kV SWGR Building Full superstructure | Superstructure columns | 77 | m³ |
| Roof beams | 115 | m³ | |
| Parapet | 63 | m³ | |
| Door canopies | 10 | m³ | |
| Double-T slab, 1000mm | 1,080 | m² | |
| Hollow core slab (600/400/250mm) | 518 / 510 / 64 | m² | |
| Insulated wall panels, 260mm | 1,290 | m² | |
| Shear wall, 260mm | 280.4 | m² | |
| Customer Room Roof-slab-only per building list, but BOQ carries full walls/columns | Hollow core slab, 400mm | 951.2 | m² |
| Insulated wall panels, 260mm | 1,944.8 | m² | |
| Ground columns / roof beams | 97.2 / 97.2 | m³ | |
| Security Equipment Building | Ground columns / roof beams | 18.9 / 16.8 | m³ |
| Hollow core slab, 250mm / Insulated wall, 260mm | 99.9 / 336 | m² | |
| Gate House | Ground columns / roof beams | 5.25 / 3.36 | m³ |
| Blast-resistant wall panel, 320mm | 92 | m² | |
| Pump House (UG Water Tank) | Columns / roof beams / HCS 400mm / wall panels | 18 / 18.3 / 93.8 / 87.2 | m³ / m³ / m² / m² |
| Yard, ducts, roads | Trench covers, splash blocks, curb stones | 325.3 / 428.5 m² · misc pcs | mixed |
Note: Unit rates and totals are blank in the tender BOQ (SAR columns not populated) — KPC is expected to price these quantities in its commercial offer. Figures above pulled directly from "Ashayrah Precast Concrete BOQ.xlsx" sheets .1–.3.
Interface Coordination & Deliverables — Where KPC Carries Risk
Watch Items| Area | What the Spec Requires of KPC |
|---|---|
| CIP Substructure Interface | KPC must fully coordinate precast-to-cast-in-place interfaces (base plates, anchor bolts, grout pockets, starter bars, bearing pads) before production starts. No production may proceed until interface sync is verified/approved by Elsewedy/NGSA — this is a hard gate that can stall fabrication if substructure design lags. |
| Structural Model & Reactions | KPC/precast manufacturer must submit full structural models, calculations, and factored/non-factored reaction forces in a format compatible with the substructure designer's software and sign convention — a non-trivial coordination deliverable, not just shop drawings. |
| RFI Discipline | Any discrepancy between precast and CIP substructure design must go through a formal technical RFI — informal site fixes are explicitly disallowed ("No modifications shall be made on site without formal written approval"). |
| Shop Drawings / Submittals | Complete precast drawings (dimensions, reinforcement, embeds, lifting inserts, erection marks, weight estimates) + structural calc packages (flexure/shear/serviceability per ACI 318M) + material pre-approval certificates (mix design, rebar, strand, grout, bearing pads). All per SEEDS-II title blocks/annotation standards. |
| Unified Design Program | NGSA is standardizing precast member sizes across all three BSP sites (Masturah / Al Asharya / Al Majmaa) with only "slight variation margin related to customized mold size" allowed per manufacturer — KPC's own mold inventory should be checked against this unified sizing before committing to unit rates. |
| Late Changes | Equipment/room/door/penetration changes affecting precast must be finalized at design stage; late changes require NG approval and revised design before shop drawings can be released — a real schedule risk if MEP/architectural finalize late. |
Not specified in provided documentsNo payment milestones, advance payment percentage, retention percentage, or payment schedule were found anywhere in the uploaded package (PTS spec, BOQ, DOR, schedule, clarification form). This is a strong candidate for a clarification request before KPC submits pricing, since payment terms materially affect the precast supplier's cash flow given significant upfront mold/material costs.
Not specified in provided documentsNo bid evaluation methodology, weighting, or qualification thresholds are included in this package — likely held at the Elsewedy PSP tender/procurement level rather than in the technical appendices provided to KPC.
Change in Scope
Internal Inconsistency Found| Building List vs. BOQ Mismatch | "Precast Building List.xlsx" tags Customer Building, Security Building, Fire Pump Building, Gate Room, and Tunnel Stairs as "Roof Slab only" scope. However, the BOQ ("Ashayrah Precast Concrete BOQ.xlsx") carries full column, beam, and insulated-wall-panel line items for the Customer Room, Security Equipment Building, and Gate House. This is a material scope-definition conflict. |
| Commercial Impact | If the wider BOQ scope is correct, KPC's pricing basis is materially larger than the "roof slab only" label suggests (e.g., Customer Room alone carries ~1,945 m² of insulated wall panel and ~194 m³ of columns/beams in the BOQ, not reflected in the building list description). |
| Recommended Action | Raise via the Clarification Form (Appendix-05) before bid submission to lock down the correct scope boundary per building — do not price silently against either document as authoritative. |
| Future Change Control | Per Appendix-25 Section 4(K), any late change to equipment/room/door coordination affecting precast must be approved by NG and reflected in a revised design before shop drawings are released — this is the formal mechanism for any change post-award. |
Not specified in provided documentsNo liquidated damages clause, daily/weekly LD rate, or LD cap was found in the tender package provided. This sits in the main subcontract agreement, which was not part of this upload — recommend requesting it before bid finalization given the tight 5-month project duration.
Customs Duties, Taxes & Logistics
From Appendix-02 (DOR), Section E| Customs Clearance & Fees | Subcontractor (KPC) scope — for both permanent Plant/Equipment/Material and temporary construction equipment, "if applicable" |
| Customs Duties & Taxes | Subcontractor (KPC) scope — same basis as above |
| Shipping & Transport | KPC responsible for shipping documents, packing/material/inventory lists, road surveys, and heavy-lift transportation for precast plant/material — relevant given large precast units (e.g., double-tee slabs, wall panels) likely fabricated off-site and moved to a Taif-region wind BSP location. |
| Unloading & Inventory | KPC responsible for unloading at both site warehouse and final installation location, unpacking inspection/reporting, and its own inventory control. |
| Commercial Note | Since customs, duties, and heavy-lift logistics sit fully with KPC, factor cross-border/import costs (if precast elements or specialized formwork are sourced outside KSA) explicitly into the unit rates rather than treating them as reimbursable. |
Not specified in provided documentsNo insurance requirements (CAR, third-party liability, professional indemnity, minimum sums insured) are addressed in the appendices provided. Typically held in the main subcontract terms — recommend confirming coverage requirements before bid, particularly professional indemnity given KPC is taking design responsibility for the structural precast system.
Not specified in provided documentsNo claims notification procedure, dispute resolution mechanism, or arbitration seat/rules are included in this package. These clauses typically sit in the commercial subcontract agreement rather than the technical appendices reviewed here.
Warranty & Guarantee Obligations
Legal Review Recommended| Guarantee Letter | Per Appendix-25 Section 2(F): "CONTRACTOR / Precast Manufacturer shall issue Guarantee Letter that precast structures elements (columns, beams, canopies, staircase, roof & parapets, HCS and TT-slab) system and its connections will be safe to be done under all cases of loadings including seismic forces, lateral forces and cast in-situ structural screed act as diaphragm." |
| Nature of Obligation | This is a structural performance warranty (not just a workmanship/materials warranty) — it effectively certifies the whole precast system's behavior under seismic and lateral loading, including its interaction with the in-situ screed diaphragm. |
| Shop Drawing Control | "No shop drawing, fabrication, or site modification is permitted without written NG/SEC approval and full interface coordination with all disciplines" — KPC has no unilateral authority to adjust details on its own once designs are approved. |
| Decorative/Architectural Finality | "All decorative or non-standard architectural features must be finalized and approved at the design stage. No late variation orders for such items will be considered" — protects KPC from late architectural changes, but also means KPC must lock in finishes early. |
| Recommendation | Have legal/insurance review the Guarantee Letter wording before signature — confirm it does not extend KPC's liability beyond standard structural design responsibility, and check professional indemnity coverage aligns with this scope. |
Division of Responsibility (Appendix-02) — Subcontractor Obligations
Broad Sub Scope| General Pattern | The DOR is written almost entirely "X = Subcontractor" — KPC (as Subcontractor) carries nearly all site-level, HSE, logistics and self-support obligations; Elsewedy PSP only carries office/labor-camp land allocation, site perimeter security, construction electricity source, fire truck/ambulance, first-aid facility, and waste-water treatment. |
| Design & Submittals | Subcontractor scope: design drawings, workshop drawings incl. bar bending schedules, as-built drawings, material submittals/certificates, sample approvals — all fully on KPC. |
| Site Facilities | KPC must provide its own labor camp, storage, workshops (land only from PSP for storage/workshop use), running costs, security/fencing of its own facilities, sanitation, first-aid clinic. |
| Lifting & Equipment | KPC is responsible for ALL temporary lifting equipment (cranes, hoists, tower cranes) including calculation sheets, plus scaffolding/shoring and hard-standing prep for cranes — significant cost and schedule item for a precast erection scope of this size. |
| Utilities | Construction water source is KPC's; construction electricity source is Elsewedy PSP's, but distribution/connection to KPC's work areas is KPC's responsibility. |
Submittal List of Documents
Appendix-25, Attachment-4| Precast Superstructure Drawings |
|
| Design Calculation Package | Comprehensive structural calculations verifying flexural, shear, and serviceability performance per ACI 318M; full structural model with factored/non-factored reaction forces compatible with the substructure designer's software. |
| Material Certificates | Pre-approval certificates for concrete mix designs, reinforcement steel, prestressing strand, grout materials, lifting inserts, embedded plates, bearing pads, and connection accessories — each referencing applicable standards and batch IDs. |
| Reference Attachments in Spec | Attachment-1: Precast Connection Details · Attachment-2: Waterproofing Details · Attachment-3: Canopy Precast Connection Details · Attachment-4: Additions to Unified Design Submittal List (Appendix-3) — all marked "conceptual/guidance only," actual dimensions/reinforcement to be engineered by KPC. |
Commercial & Bid Strategy Notes
For PropelPro / Dimensionless Support| Pricing Basis | BOQ quantities are provided but unit rates (SAR) and totals are blank — this is a rate-and-total tender; KPC needs to submit its own unit pricing sheet against the ~90 line items across sheets .1–.3. |
| Repeatability Angle | Because the precast typology is being unified across Masturah, Al Asharya and Al Majmaa, KPC could price a mobilization/mold-amortization discount if bidding for multiple sites, or flag this as a negotiation lever if only bidding Al Asharya alone. |
| Schedule Risk | Overall project duration is only 5 months per Appendix-01 — very tight for full-superstructure precast (GIS + Control buildings) given the CIP interface gating condition ("no production until interface sync verified"). Recommend an explicit RFI/clarification on substructure design freeze dates before committing to this duration. |
| Warranty Exposure | The mandatory Guarantee Letter (Section 2-F) covering seismic/lateral/diaphragm performance of the full precast system is a structural performance warranty, not just a workmanship one — legal/insurance review recommended before signature. |
| Open Items to Clarify | (1) Actual commencement/delivery dates (schedule sheet blank); (2) the roof-slab-only vs. full-BOQ scope conflict flagged under "Change in Scope"; (3) payment terms, LDs, insurance and dispute clauses — none of which appear in this technical package and should be obtained from the commercial subcontract agreement. |